AnHui HuaSu Thermal Power Plant reached its full capacity
At 20:30 on June 27, the Unit # 1of Anhui HuaSu Thermal Power Plant reached its full capacity--300MW for the first time with all the parameters being normal. It is an important milestone which represent that the Unit # 1 has reached the designing output, and then the 168 hours performance test may start in order. The whole operation of Anhui HuaSu Thermal Power Plant is undertaken by WOM.
The following test will be the boiler rating output without high heaters . And then, the generator experiments and CCS commissioning will be in progress. WOM has a thoughtful arrangement for Huasu Project, all the operators of WOM operated in accordance with the instructions of commissioning programs. Our staff has find a lot of defects of the unit such as leaking of feed pump oil, mill hydraulic oil in the first time. The high quality operation of WOM has been the guarantee of the unit performance.(by Huang Xia)