Xiexin Project Department of WOM started urgent repair to coal conveyor belt #2C(Phase Ⅱ), 17th March.
This replacement of belt #2C was characterized by heavy work and tight schedule. During repair, working groups would rectify defects and do some routine maintenance of coal handling system, like periodic repair to motor 2C-3 of belt #2C, couplers disconnection of 4 belt motors and dismantling a speed reducer to send it to repair in OEM. Compared with PhaseⅠ, the workload had doubled with 10 workdays. So Project Department had made thorough preparation before starting work, specifying maintenance procedures, requirements for technology, time schedule and safety measures and appointing persons in charge of each work section to ensure repairing work would go on systematically.