新闻中心

基层动态

您当前的位置: 网站首页 > 新闻中心 > 基层动态

The urgent repair to coal conveyor belt in Xiexin Project Department of WOM started

发表时间:2014年03月19日   阅读数:1497

    Xiexin Project Department of WOM started urgent repair to coal conveyor belt #2C(Phase Ⅱ), 17th March.
    This replacement of belt #2C was characterized by heavy work and tight schedule. During repair, working groups would rectify defects and do some routine maintenance of coal handling system, like periodic repair to motor 2C-3 of belt #2C, couplers disconnection of 4 belt motors and dismantling a speed reducer to send it to repair in OEM. Compared with PhaseⅠ, the workload had doubled with 10 workdays. So Project Department had made thorough preparation before starting work, specifying maintenance procedures, requirements for technology, time schedule and safety measures and appointing persons in charge of each work section to ensure repairing work would go on systematically.

 



相关附件:

公司地址:合肥市高新区海棠路150号创新大厦17楼  联系电话:+8655162587766
版权所有©2010   备案号:皖ICP备10202915号-1   皖公网安备 34019202001262号