The Completion of WOM Vietnam QuangNih Project Second Phase Unit 4# Steam Blowing
The steam blowing work has been performed for WOM QuangNih second phase Unit 4# after the acid and alkaline cleanings. The blowing can be divided into to 2 phases, during the first phase, the steam blow has been performed for 50 times, and it has been performed for 33 times in second phase, in this phase, the HP bypass has been blew for twice and boiler sootblow pipe has been blew for once.
The steam blowing has been finished at 14:07 of August 18th, with the witness of both parties, the test met the high quality requirements. This activity is a important base of Unit 4# startup, moreover, it ensured the smooth handover of the 2 units of QuangNih Phase 2 in the future.