The optimization of WOM Xinji project
Nowadays, with the consideration and discussion of WOM Xiji project leadership, they decide to optimize the generator system of the project to ensure the safety and efficiency. During the troubleshooting outage before winter, they decide to replace the industrial water with circulating water, and install the DN100mm pipe between industrial water pump outlet and circulating water main pipe, this activity achieved the replacement of water during the normal operation, for a single year unit operation (6000hr), 90000KWH will be saved, the efficiency and beneficial of this optimization is appearently.