WOM Changji project company's power plant #1 unit C repair work has entered a critical stage at present. Facing the huge pressure of tight construction period and heavy task, Changji project company still insists on strict maintenance quality control to ensure "zero defect" maintenance.
During the inspection of a and B booster pump motors of unit 1, the electrical team found that the insulation of the tap line of B booster pump motor of unit 1 was seriously damaged, and the damaged position was relatively concealed. If not found in time, the ground short circuit of B booster pump motor in the later operation caused the booster pump to trip and the feed pump to trip, which would cause major safety hazards of Rb action of the unit.
WOM Changji project company electrical team of Changji project company was meticulous and did not leave any dead space in the process of maintenance, and found major safety hazards, which was highly recognized by the owner.(Liu Yuanli)
Company Addrss: 17th floor, Chuangxin Building, 150 Haitang Road, High-tech zone, Hefei
Telephone: +86 551 6258 7766
Copy rights©2010