On the evening of May 16th, a long-distance leakage occurred in the inlet pipe of the domestic water tank of the Beiyi Power Plant in Wucaiwan, Datang, Xinjiang, which seriously affected the safety of the water used by the workers in the plant area. After receiving the rush repair task, the Wucaiwan Project Department of WOM company, under the careful organization of Ms. Ye Mei, the project manager, arranged personnel for rush repair immediately. After six hours of uninterrupted efforts, the defects were eliminated by 11:00 p.m. and the normal supply of domestic water was ensured.
Subsequently, the leader of Datang Beiyi Power Plant sent a letter of praise to WOM Company, praised the work of WOM Wucaiwan Project Department in Xinjiang, and hoped that all the staff of the Project Department would make further efforts to make greater contributions to the protection work of Wucaiwan Beiyi Power Plant in Datang, Xinjiang.