WOM Cilacap Project Successfully Perform Boiler Blowpipe

01/14/2016

        On Nov 30, 2015, the blowpipe work of two 660MW units in Cilacap began. Till Dec 23, the blowpipe of super heater met the demand. And each system was ready to be adjusted. The staffs were prepared to blowpipe the reheater. On Dec27, when all the conditions were ready to blowpipe, temporary crashing gate appeared fault and the blowpipe was forced to stop.
        Until 22:00 on Jan 9, 2016, the fault was exterminated. The reheater began to blowpipe after boiler ignition. At 14:00 on Jan 11, the three continuous shooting of reheater blowpipe marked the success in unit main pipe system and reheater system.
        During the blowpipe of reheater, due to the sudden fault, besides 8 staffs returned China for yearly holidays, the recovery faced extreme lack of operators. Vice manager Ma junhui has kept watch the site situation, coordinated and handled any possible issues that may happen. All operators were required to get in 12h shifts. For major operations, system start or stop, the related engineers must attend the work. Under the leadership of boiler engineer Yao xingling, boiler operator Zhang zhiping and Liang shaoqiu kept working for 36 hours until the blowpipe ended. For operations from other majors, they were prepared for help with unified pace. Their spirit of obeying arrangement and diligent working to ensure the success of blowpipe gained great praise and favorable reception from all members.

 


Company Addrss: 17th floor, Chuangxin Building, 150 Haitang Road, High-tech zone, Hefei Telephone: +86 551 6258 7766
Copy rights©2010