At Indian time 20:30, on October13, TPCIL power plant was full of sound of applause and cheers. Unit 2 passed the 14-day running test! WOM staffs, DEC contractor, commissioning company and electric power construction enterprise were happily sharing the joy of success.
Since the running trial of Krishnapatnam unit 2 at 20:30 on September 29, unit had been running steadily. Till that night of ending run test. The total electricity was 222868.8MW, with load rate reaching 100.5%, almost running 14 days with full load. The result indicated the good quality of the world second supercritical and half-supercritical unit. Behind the success, it was the cooperation of WOM staff, commissioning company and Construction Company that provided technical support for guiding and supervision.
The hardship and payment of success was always invisible. The process of running test was not smoothly. The boiler and turbine both had some problems which affected the operation. In order to ensure the success of running test, WOM staff kept eyes on the equipment for any possible problem regardless of the high temperature. They took measures to solve problems in time before getting more serious.
They also measured the vibration and temperature of main and auxiliary equipment of turbine, and reported to Indian owner if any abnormal situation was found.
After passing through running test of unit 2, the commissioning staff began to leave. The operation working was also transferred to WOM. The task became more difficult plus the operation and maintenance of unit 1. WOM staff enhanced the spirits of development, efficiency, innovation and leadship, gave full heart to local project and kept working hard to ensure all work could be finished.