Unit #2 in TPCIL, Krishnapatam, India, was started once again with defects attended and synchronized successfully at 20:30 local time on September 29, marking final stage of RT and significant progress since the unit passed COD on September 13.
During Unit #2 trial run of RT, most staff members in project department returned to China for renewing visa. In order to achieve passing of RT and move forward, staff on duty at site made every effort and worked double shifts to supervise operation in cooperation with commissioning department so as to ensure unit was running in a safe and sound manner. In this way, project department commemorated the 66th anniversary of founding of the People’s Republic of China, which falls on October 1.