The newly-built unit ignition blowing in power plant is an important milestone during the period from unit under construction to operation, indicating the new unit will shortly start up as a whole. According to the general plan of ICDAS power plant commissioning headquarters, unit #2 ignition blowing is set to conduct in late May. Boiler #2 initial ignition won a great sucesss at 0:15 on 23rd May local time. The joint cooperation among WOM Turkish project department and other construction units shortens greatly the time spent on unit #1 blowing, and only one week was occupied with unit #2, which has saved much time for the following start-up of the whole unit.