Project department occupied in attending defects
08/10/2015
WOM Hwasu project company performed planned outage of unit #1 to attend defects in a comprehensive way.
It aimed at handling the following issues, low vacuum in condenser, loose terminal box of 10KV motor, and dirty filter and inner leak valve in BOP etc. Maintenance department made efforts to clean filler in chilled water tower and MCC cabinet, fill condenser with water to check leakage, repair inner leak valve and bearing #6 in turbine-generator(TG), conduct anti-corrosive treatment for FGD and inner inspection of furnace, and tighten terminal box of 10KV motor etc. in orderly manner so as to ensure safe operation of unit during summer peak.